MUGOYA CONSTRUCTION CONSTRUCTION 10 BRIDGES ALONG MOMBASA ROAD, KABARAK UNIVERSITY DECEMEBR 2003 TO APRIL 2005 COMPLETE 
STEEL STRUCTURES LTD
  •  PREPARATIONS OF PLANNING DRAWINGS AS BUILTS DRAWINGS AND SITE SURVEYS
  • PREPARATION OF FABRICATION DRAWINGS
  • PREPARATION OF WORKING DRAWINGS
MAY 2005 – AUGUST 2007 COMPLETE
BARAN TELECOMS K. LTD
  •  BUILDING OF GSM SITES
  • INSPECTION OF TOWER FOUNDATIONS
NOVEMBER 2009

COMPLETE

COMPLETE

MURUGA INVESTMENT
  •  WATER RETICULATION
JANUARY 2010 COMPLETE
HOUSE OF MANJI FACTORY REHABILITATION
  •  TERAZZO FLOORS, NEW ROOF CONSTRUCTION
FEBRUARY 2010 COMPLETE
CITY COUNCIL OF NAIROBI
  •  WORK ORDERS IN DIV 3
SEPTEMBER 2010 COMPLETE
CITY COUNCIL OF NAIROBI
  •  SUPPLY OF SAFETY GEAR
JUNE 2010 COMPLETE
KONTEL LIMITED
  •  BUILDING OF GSM SITE
  • INSPECTION OF TOWER FOUNDATION
  • SUPPLY OF SAFETY GEAR

MARCH 2011

 

ON GOING

COMPLETE

COMPLETE

ON GOING

GLOBALTEL ENGINEERING
  •  SUPPLY OF ELECTRICAL MATERIALS
  • PUTTING UP RESIDENTIAL APARTMENTS IN KIGALI RWANDA
JULY 2010 COMPLETE
QUORANDUM LIMITED
  •  BUILDING OF GSM SITES
  • INSPECTION OF TOWER FOUNDSTIONS

APRIL 2010

NOVEMBER 2009

COMPLETE

COMPLETE

LINKSOFT KENYA
  •  BUILDING OF GSM SITE
  • INSPECTION OF TOWER FOUNDATION
  • SUPPLY OF SAFETY GEAR

MARCH 2010

JANUARY 2010

SEPTEMBER 2010

COMPLETE

COMPLETE

COMPLETE

KITUI CDF
  •  REHABILITATION OF ROADS
AUGUST 2010 COMPLETE
GARISSA CDF
  •  REHABILITATION OF ROADS
MARCH 2010 COMPLETE
AM-TM CONSTRUCTION LTD
  •  BRIDGE CONSTRUCTION IN KAKAMEGA COUNTY
SEPTERMBER 2010 COMPLETE
BELGRAVIA,ZAMBIA
  •  CONSTRUCTION OF OIL DEPOTS AT LUSAKA, NDOLA, MPIKA AND SOLWEZI
JULY 2011 TO DECEMBER 2013 COMPLETE
NDOLA ENERGY
  •  CONSTRUCTION OF 50MW HFO PLANT AT NDOLA
APRIL 2012 TO DECEMBER 2013 COMPLETE
KENYA PIPELINE
  •  CONSTRUCTION OF ADDITIONAL TRUCK BOTTOM LOADING FACILITIES AT PS 27 - ELDORET DEPOT
MARCH 2014 TODATE ON GOING